Robbins TBM completes ‘record’ run on tunnel project

By Catrin Jones25 March 2022

A Robbins Single Shield Tunnel Boring Machine (TBM) has completed a record-setting 3.5km run in sedimentary rock below Lake Ontario for the Ashbridges Bay Outfall in Toronto, Ontario, Canada.

The project won accolades from the Tunnelling Association of Canada (TAC) in late 2021 for its all-remote machine acceptance enacted due to the Covid-19 pandemic, said Robbins (Photo: Robbins)

The machine project, for the Southland/Astaldi JV, began in March 2021 at 85m deep and 16m diametre shaft, boring initially into predominantly shale - with limestone, siltstone, and sandstone.

The completed outfall will connect to the 50 in-lake risers to enable efficient dispersion of treated effluent over a wide area of the lake. The project, for the City of Toronto, was completed with the aim to improve the city’s shoreline and Lake Ontario’s water quality by replacing existing outfall.

Alfredo Garrido of Robbins Field Service, said, “This is a wonderful type of geology for our machines. During the entire excavation, a total of 7 cutters were changed. The wear behaviour is incredible, between 2 and 5 mm, and everyone is amazed by the cutter performance.”

A Robbins continuous conveyor system, including a vertical conveyor, transported muck behind the machine. “Every 25 machine cycles, it was necessary to stop the excavation to probe drill hole in front of the cutterhead to check for possible water. This drilling was done basically every day, stopping the machine for a few hours, but it was very necessary,” added Garrido.

MAGAZINE
NEWSLETTER
Delivered directly to your inbox, World Construction Week Newsletter features the pick of the breaking news stories, product launches, show reports and more from KHL's world-class editorial team.
Longer Reads
The four big takeaways from ConExpo 2023
The four big takeaways to emerge from the year’s largest construction equipment show.
Safe slab and beam shoring starts before installation
Shoring best practices from SAIA lead with critical questions any project needs answered in detail to shore safely
How is Turkey planning to rebuild after a devastating earthquake?
It’s now over a month since two earthquakes in rapid succession devastated parts of Turkey and neighbouring Syria.
CONNECT WITH THE TEAM
Andy Brown Editor, Editorial, UK - Wadhurst Tel: +44 (0) 1892 786224 E-mail: andy.brown@khl.com
Neil Gerrard Senior Editor, Editorial, UK - Wadhurst Tel: +44 (0) 7355 092 771 E-mail: neil.gerrard@khl.com
Simon Kelly Sales Manager Tel: +44 (0) 1892 786 223 E-mail: simon.kelly@khl.com
CONNECT WITH SOCIAL MEDIA