Progress on hydroelectric plants in Bhutan

05 March 2020

2020-03_BAUER_Punatsangchhu-2 Bhutan (1)

Bauer is working on the construction of the hydroelectric plant

The Kingdom of Bhutan, located north of India, is pursuing an ambitious and sustainable energy policy, including the construction of the large-scale Punatsangchhu-1 hydroelectric plant with the help of Bauer Spezialtiefbau GmbH.

Bhutan is barely the size of Switzerland and dominated by the Himalayas, the highest mountains in the world. Over 80% of Bhutan is 2,000m above sea level.

Mountains with a height of up to 7,500m mark the highest points of the country. Many rivers span several thousand metres in altitude as they make their way from north to south, creating ideal conditions for hydroelectric power. Bhutan already generates almost all of its electricity from hydropower, with the surplus being exported to neighbouring India.

Construction work has been underway on the Punatsangchhu-1 project since 2009 and Punatsangchhu-2 in 2013. Both hydroelectric plants are located on the Puna Tsang Chhu River, approximately 80 and 94 km from the capital Thimphu.

In 2011, Bauer constructed diaphragm walls up to 80m deep for the upstream cofferdam and executed injection work on Punatsangchhu-1. The company returned to the site a few years later to carry out slope stabilisation after a massive landslide on the right bank of the river.

In 2014, Bauer was contracted to execute injection work to seal the Punatsangchhu-2 upstream cofferdam, a project that was successfully completed in 2015.

“The Punatsangchhu-2 project involves the construction of a 90m high dam, an 8.5km long pressure tunnel and several caverns in the power plant complex,” says Frank Berner, operations manager at Bauer.

2020-03_BAUER_Punatsangchhu-2 Bhutan (2)

Bauer was again contracted to carry out specialist foundation engineering work for the project after an underground cavern collapsed at Punatsangchhu-2. The company was commissioned by main contractor Jaiprakash Associates Limited to carry out 18,000m of soil injection for subsoil stabilisation as well as to install 19,000 m of tie-back anchors. Along with various equipment for the injection work, up to five drilling rigs are being used at the same time, including KR 806 and KR 909 rigs from KLEMM Bohrtechnik GmbH.

“The main challenge of this project is the cramped working environment. With a width of approximately 18m and a height of 8m, the work area is extremely small, creating an extremely challenging environment for equipment and personnel,” continues Berner. “Also, we’re in the Himalayas, which presents unique challenges for logistics.”

Bauer’s work on Punatsangchhu-2 will take around 15 months.

STAY CONNECTED



Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

Sign up

CONNECT WITH THE TEAM
Andy Brown Editor, Editorial, UK - Wadhurst Tel: +44 (0) 1892 786224 E-mail: [email protected]
Neil Gerrard Senior Editor, Editorial, UK - Wadhurst Tel: +44 (0) 7355 092 771 E-mail: [email protected]
Catrin Jones Deputy Editor, Editorial, UK – Wadhurst Tel: +44 (0) 791 2298 133 E-mail: [email protected]
Eleanor Shefford Brand Manager Tel: +44 (0) 1892 786 236 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA