Final breakthrough for Mumbai’s US$4.2 billion Metro Line 3

By Andy Brown22 July 2021

A 6.6m (21.8ft) diameter Robbins Crossover XRE TBM

A 6.6m (21.8ft) diameter Robbins Crossover XRE TBM has made its third and final breakthrough for India’s Mumbai Metro Line 3. The project has an estimated cost of US$4.2 billion. 

The crew and equipment had to overcome unpredictable terrain, high-pressure water ingress, and government-imposed lockdown orders during the Covid-19 pandemic.

The project is a joint venture between Larsen & Toubro and the Shanghai Tunnel Engineering Company. 

The two custom-built machines were selected to bore parallel 2.9km (1.8 mile) tunnels between the Cuffe Parade station and CST stations, breaking through into several station sites along the way.

“It is the first time in India that Dual Mode, Crossover type TBMs equipped with a horizontal screw conveyor and high torque high speed (two-speed) cutterhead drives were used. Overall, the performance of the Crossover TBMs was found satisfactory and we are in the process of shifting these TBMs for the L&T Chennai Metro project,” said Palwinder Singh, head of tunnel construction for the L&T – STEC JV.

In another first for India, the Crossover TBMs employed a unique technique in a 554m (1,820 ft) long section from Hutatma Chowk to CST stations. They were used in the benching of the NATM Platform tunnel through basalt rock (removal of the bottom section of rock remaining in the station after conventionally removing the top section).

As the financial capital of India and one of the most populated cities in the world, Mumbai is faced with an excessive amount of road traffic. It currently takes up to two hours to drive the 25km (15mi) distance from Cuffe Parade to the airport – the same trip on the finished metro will take 50 minutes.

The completion of Mumbai Metro Line 3, which is expected in 2025, will save residents transit time and is expected to initially decrease road traffic in the area by 35%, reducing daily fuel consumption by 460,000 liters.

MAGAZINE
NEWSLETTER
Delivered directly to your inbox, World Construction Week Newsletter features the pick of the breaking news stories, product launches, show reports and more from KHL's world-class editorial team.
Longer Reads
When will the China access market reach maturity?
The Chinese MEWP sector is still growing quickly, at around 40% year-on-year, but is several steps from maturity 
GCCA reveals 7 ways to reach concrete ‘Net Zero’
The world’s leading cement and concrete manufacturers have made a global commit to cut CO2 emissions by a further 25% by 2030
Why the rental sector is expanding its services
Major equipment rental companies around the world are extending the services they can offer
CONNECT WITH THE TEAM
Andy Brown Editor, International Construction Tel: +44 (0) 1892 786 224 E-mail: andy.brown@khl.com
Simon Kelly Sales Manager Tel: +44 (0) 1892 786 223 E-mail: simon.kelly@khl.com
CONNECT WITH SOCIAL MEDIA