Construction Milestones
06 February 2009
The Golden Ears Bridge project is an initiative of TransLink, the South Coast British Columbia Transportation Authority. The scheduled opening date for the bridge is mid-2009. The timing of all construction activities is subject to permitting and approval by government authorities.
April 2006
Golden Crossing Constructors Joint Venture begins pre-construction activity with test work north and south of the Fraser River.
June 27, 2006
Joint Venture, TransLink and Golden Crossing General Partnership officially launch construction activity.
Spring to Autumn 2006
Survey work to establish construction corridor.
Summer 2006
Work begins to build the projects main bridge, in the Fraser River - soil densification in preparation for pile boring.
Clearing for Golden Ears Route begins in the unnamed creek area, west Port Kells (Surrey), and in the Westcon area between Telegraph Trail and 199A Street along the south side of the Canadian National rail tracks.
Start of preloading for northern connector road, Maple Ridge.
Autumn 2006
Piling begins in the river at the southern most bridge pier site. This work then moves from south to north across four pier sites.
Start of preparatory work for overpasses of the Golden Ears Route at the Trans-Canada Highway and Barnston Drive, Surrey.
Start of piling for Westcon elevated roadway, Surrey/Langley border.
Late 2006
Completion of piling at Westcon; columns and abutments appearing.
Start of piling for north bridge approach, Maple Ridge.
Clearing for new connecting road from 201 Street to 199A Street, Langley.
Clearing for Lougheed Highway Interchange, Maple Ridge/Pitt Meadows border.
Early 2007
Start of northwest Langley road improvements -- 201 Street upgrades and connecting route from 199A Street to 200 Street.
Clearing in the Anniedale section of the Golden Ears mainline route (Trans Canada to 176 Street, Surrey).
Drainage work for the Lougheed Highway Interchange, Pitt Meadows.
Start of improvements to 96 Avenue between Telegraph Trail and 201 Street, Langley.
Spring 2007
Opening of 201 Street to 199A Street Connector, Northwest Langley; implementation of one-way traffic loop on 201, 199A and 200 Streets.
First girders at Westcon overpass, Langley
Start of improvements to 192 Street, Surrey.
Utility work and earthworks on Golden Ears mainline, 176 Street to 182 Street, Surrey, plus temporary traffic pattern changes to the Anniedale street network
Start of piling for the south bridge approach, 201 Street North, Langley.
Completion of main bridge piling work, Fraser River.
Major utility relocation for the Northern Connector between 113B Avenue and the south end of Maple Meadows Way, Maple Ridge
Clearing for the Abernethy Connector western section, Lougheed to 203 Street, Pitt Meadows/Maple Ridge
Summer 2007
Earthworks continue for Golden Ears Route, 176 Street to Trans Canada, Surrey
Resume construction for the Trans Canada and Barnston Drive overpasses of the Golden Ears Route
Earthworks begin, Golden Ears Route, 192 Street to Telegraph Trail
Begin piling for 199A Street off ramp, Langley
Begin piling for 201 Street on ramp, Langley
Begin girder installation for south bridge approach near 100A Avenue, Langley
Completion of north bridge approach precast piling, Maple Ridge
Reconstruct Dunn Avenue, Maple Ridge.
Clearing for Meadowtown Viaduct, Maple Ridge/Pitt Meadows border, and construction road from Dunn Ave. to Lougheed Highway
Start of piling for Meadowtown Viaduct, Canadian Pacific Rail overpass and Lougheed Highway overpass, Maple Ridge/Pitt Meadows border
Complete road base for Abernethy Connector west of 203 street; clear and begin preloading west of 210 Street
Autumn 2007
Implement permanent street network changes in Anniedale neighbourhood (Surrey) and pave Golden Ears Route from 176 Street to 182 Street
Begin reconstruction of Trans-Canada Highway sections to create overpasses of the Golden Ears Route
Earthwork and roadwork for connector from 96 Avenue to Golden Ears Route, Surrey
Begin widening of 200 Street from 92A Avenue to Chevron station, Langley
Complete piling for 201 Street on ramp and 199A Street off ramp, Langley
Construction on southernmost in-river tower reaches deck level
Haul 100,000 cubic metres of fill to create base for Lougheed Highway interchange
Install monopile foundations for Lougheed Highway overpass
Closure of Maple Meadows Way from Dunn Avenue to 200 Street to allow major utility relocation, road work and construction of off ramp
Winter 2007-2008
First bridge deck panels placed
First bridge deck stay cables placed
Completion of first bridge tower at M2, off the Langley shore
Complete foundations for Highway 1 and Barnston overpasses
Place first girders for Highway 1 and Barnston overpasses
Open new 199A Street to 200 Street connector, Langley
Complete girder installation, south bridge approach plus south on and off ramps
Begin girder installation, north bridge approach
Piling and earthworks begin for 113B Avenue/Airport Way interchange, Maple Ridge/Pitt Meadows
Complete foundations for Meadowtown Viaduct
Columns and crossbeams, CP Rail overpass
Piling for Maple Meadows Way off ramp
Spring 2008
Close first span of main bridge, from tower M2 in Fraser River to tower M2 on land
Complete deck panel installation for south bridge approach and ramps, Langley
Complete girder installation, north approach
Begin girder installation, Meadowtown viaduct
Begin piling for bridge at un-named creek, Surrey
Completion of Westcon overpass, Surrey/Langley
Widening and improvements, 201 Street North (under south approach), Langley
Piling for Lougheed Highway off ramp to Meadowtown viaduct
Complete road base for Abernethy connector, 203 Street to 210 Street
Summer 2008
Close second span of main bridge deck between towers M2 and M3
Girder installation over Lougheed Highway
Complete paving of mainline, 186 Street to Telegraph Trail, Surrey
Telegraph Trail realignment, Langley
Completion of 199A Street off ramp and 201 Street on ramp decks, Langley
Completion of south bridge approach deck, Langley
Improvements at 210 Street and 132 Avenue intersection, Maple Ridge
Bicycle and pedestrian path construction, Surrey and Pitt Meadows
Autumn 2008
Completion of main bridge deck between towers M3 and M4, and between M4 and M5
Completion of Golden Ears Route, Surrey
Completion and opening of Barnston and Trans-Canada Highway overpasses, Surrey
Completion of street improvements, 192 Street, Surrey
Begin street and interchange improvements on 200 Street north and south of the Trans-Canada Highway, Langley
Completion of deck for 201 Street on ramp, Langley
Construction of 201 Street and 100A Avenue roundabout, Langley
Completion of north approach deck, Maple Ridge
Placement of girders and deck panels on 113B Avenue overpass
Construction of Hammond Road/Maple Meadows Way roundabout, Maple Ridge
Completion of CP Rail overpass deck, Meadowtown viaduct deck and Maple Meadows Way off ramp deck
Completion of Lougheed Highway overpass deck and deck for for Lougheed Highway off ramp to Meadowtown Viaduct, Pitt Meadows
First paving of Abernethy Connector from Lougheed interchange to cattle underpass near 210 Street
Construction of culvert for cattle underpass
Late 2008/Early 2009
Completion of main bridge deck, closing spans from M5 to M4 and M5 to M6
Completion of bridge at un-named creek, Surrey
Completion of 199A Street off ramp
Construction of sound walls on 200 Street near TCH, and opposite Wildwood Crescent, Pitt Meadows
Completion of 113B overpass, roundabouts at 113B Avenue and Airport Way, and ramps to mainline
Final paving of Abernethy Connector and completion of 210 Street/128 Avenue intersection.
Installation of lighting and signage on main bridge and all structures, with full operation to begin in summer 2009.
© 2007 The Golden Ears Bridge
STAY CONNECTED
Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.