Bidding on Belo Monte Dam suspended

By Steve Skinner16 April 2010

A Brazilian federal court judge has suspended bidding for the construction and operation of the Belo Monte Dam on the Xingu River in the Amazon.

The ruling has resulted in the suspension of the hydroelectric project's environmental licence that was granted by the Brazilian Institute of Environment and Renewable Natural Resources (IBAMA) in February this year.

Brazilian president Luiz Inacio Lula da Silva has vowed to appeal the ruling. Executive director of pressure group Amazon Watch, Atossa Soltani said, "Everyone recognises that in Brazil a decision like this could be overturned quickly, so we clearly haven't won the battle yet."

Bidding by a single consortium for the construction and operation contract was scheduled to take place on 20 April, but the judge said that more time was needed to examine claims that indigenous people were not consulted about the project and that insufficient clauses regarding environmental protection were in place.

MAGAZINE
NEWSLETTER
Delivered directly to your inbox, World Construction Week Newsletter features the pick of the breaking news stories, product launches, show reports and more from KHL's world-class editorial team.
Longer Reads
10 ways to join the hydrogen power revolution
Interest in the use of hydrogen has soared over the past few years as the construction industry races to reduce its carbon footprint. We roundup some recent initiatives
Telescopic boom lifts - the trends
Higher capacities and 100% electric models are the trend. And what lies ahead for 200ft models, or above?
How construction can become sustainable
The construction industry is undergoing a transformative shift to adapt more environmentally friendly practices
CONNECT WITH THE TEAM
Andy Brown Editor, International Construction Tel: +44 (0) 1892 786 224 E-mail: andy.brown@khl.com
Simon Kelly Sales Manager Tel: +44 (0) 1892 786 223 E-mail: simon.kelly@khl.com
CONNECT WITH SOCIAL MEDIA