Report finds construction problems with cancelled US$9 billion Keystone pipeline

A supply depot servicing the Keystone XL crude oil pipeline lies idle in Oyen, Alberta, Canada, February 1, 2021. REUTERS/Todd Korol/File Photo

Multiple problems with the construction, manufacture and design of the Keystone Pipeline validate President Joe Biden’s decision to revoke the permit for the US$9 billion Keystone XL extension, according to a report. 

Several House Democratic committees requested a report by US government watchdog Government Accountability Office (GAO) in November 2019 after more than 11,000 barrels of oil leaked from the pipeline system in two releases in less than two years, Reuters reported.

“GAO found that preventable construction issues contributed to the current Keystone pipeline’s spills more frequently than the industry-wide trends,” they said in a statement.

Keystone’s four largest spills were “caused by issues related to the original design, manufacturing of the pipe, or construction of the pipeline,” the GAO report said.

Biden cancelled Keystone XL’s permit on his first day in office on January 20, dealing a death blow to a project that would have carried 830,000 barrels per day of heavy oil sands crude from Alberta to Nebraska. 

Approximately 1,000 construction jobs were eliminated as a result of the revocation. About 93 miles of pipe had been installed and an additional 1.4 miles had been completed at the Canada-US border as of the end of 2020.

Canada-based TC Energy owns the existing Keystone oil pipeline and also operates the largest integrated natural gas pipeline system in North America, stretching from British Columbia to Mexico. According to the company’s 2019 annual report, Keystone XL development costs were US$1.5 billion from January 2018 through December 31, 2019.

TC Energy officially cancelled Keystone XL in June. It filed a notice of intent in July to begin a legacy North American Free Trade Agreement claim and is seeking more than US$15 billion in damages from the US government.

STAY CONNECTED



Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

Sign up

CONNECT WITH THE TEAM
Andy Brown Editor, Editorial, UK - Wadhurst Tel: +44 (0) 1892 786224 E-mail: [email protected]
Neil Gerrard Senior Editor, Editorial, UK - Wadhurst Tel: +44 (0) 7355 092 771 E-mail: [email protected]
Catrin Jones Deputy Editor, Editorial, UK – Wadhurst Tel: +44 (0) 791 2298 133 E-mail: [email protected]
Eleanor Shefford Brand Manager Tel: +44 (0) 1892 786 236 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA