LA pays $ 300 m to settle claim with Kiewit

By Mike Hayes14 December 2016

The Los Angeles Metropolitan Transportation Authority (Metro) has paid US$ 300 million to settle its protracted dispute with contractor Kiewit.

Kiewit was seeking US$ 518 million in a combination of extra charges and compensation, following its work on upgrading a section of Interstate 405.

The firm claimed Metro had been in breach of its contract, when it failed to warn it about nine miles of underground utility lines – as well as a drainage culvert – that had to be protected during the construction process.

It further claimed Metro had made repeated changes to the design of the project, after construction work had begun, creating “staggering” expenses.

To fulfil its contract, Omaha-based Kiewit was forced to double the workforce on the project – which has now risen to around US$ 1.6 billion.

After both parties submitted their dispute to arbitration, Metro agreed to the settlement of US$ 300 million.

Metro’s chairman, John Fasana, said, “Metro could have continued to negotiate the settlement but we had some culpability, and it was time to move forward.”

MAGAZINE
NEWSLETTER
Delivered directly to your inbox, World Construction Week Newsletter features the pick of the breaking news stories, product launches, show reports and more from KHL's world-class editorial team.
Longer Reads
What will the cities of the future look like?
The world’s biggest cities will be located in different areas than today and will also look considerably different 
The digitalisation of the construction industry
Trackunit looks at key trends in the cohesive development of construction technology
Demolition or refurbishment?
Increasing numbers of politicians and architects are favouring reused buildings over demolition
CONNECT WITH THE TEAM
Andy Brown Editor, International Construction Tel: +44 (0) 1892 786 224 E-mail: andy.brown@khl.com
Simon Kelly Sales Manager Tel: +44 (0) 1892 786 223 E-mail: simon.kelly@khl.com
CONNECT WITH SOCIAL MEDIA