Excavation starts on Istanbul’s Eurasia Tunnel

By Chris Sleight22 April 2014

Excavation using a 13.7 m diameter Herrenknecht tunnel boring machine (TBM) has started on the Eurasia Tunnel in Istanbul. The US$ 1.25 billion project will connect the European and Asian sides of the city across the Bosphorus, and will be the first tunnel between the two continents.

The TBM was launched on Saturday 19 April from the Asian side of the crossing. The launch ceremony was attended by Turkish Prime Minister Recep Tayyip Erdoğan and Minister of Transport, Maritime Affairs and Communications, Lütfi Elvan.

Construction of the link is being carried out by the Avrasya Tüneli İşletme İnşaat ve Yatırım A.Ş. (ATAŞ) consortium, which comprises Turkey’s Yapi Merkezi and SK Engineering & Construction from South Korea. Advance rates in the region of 7 m per day are expected on the tunnel excavation.

The link will 14.6 km in total with a 5.4 km tunnel section. When complete the tunnel will have two decks and will be open to light four-wheeled vehicles. Heavy vehicles and two-wheel vehicles will still use the existing Bosphorus bridge. Completion is expected in October 2016.

The scheme is being built on a build-operate-transfer (BOT) model by ATAS, under a 30 year, six month concession period, the first 55 months of which will be taken-up by construction. Financing for the scheme has come from a variety of multi-lateral institutions, including the European bank for Reconstruction and Development, (EBRD), European Investment bank (EIB) and the Export-Import Bank of Korea, as well as private financial institutions.

MAGAZINE
NEWSLETTER
Delivered directly to your inbox, World Construction Week Newsletter features the pick of the breaking news stories, product launches, show reports and more from KHL's world-class editorial team.
Longer Reads
How can employers overcome skills shortages and fill vacancies?
As the pandemic further exacerbates problems finding good new employees, how can employers fill vacancies? 
How is digitisation changing the falsework and framework process?
Digitisation is taking hold in several areas of the falsework and formwork process, enabling the sector to increase efficiency, reduce costs and plan even more ambitious projects
Is construction taking slave labour seriously?
The International Labour Organisation estimates that 4.5 million people are currently working in construction against their will
CONNECT WITH THE TEAM
Andy Brown Editor, International Construction Tel: +44 (0) 1892 786 224 E-mail: andy.brown@khl.com
Simon Kelly Sales Manager Tel: +44 (0) 1892 786 223 E-mail: simon.kelly@khl.com
CONNECT WITH SOCIAL MEDIA