‘Errors in design’ caused Florida bridge collapse

By Andy Brown25 October 2019

137234_floridabridge_615612

The bridge collapsed due to a ‘errors in design’

The National Transportation Safety Board (NTSB), an independent Federal government agency in the US, has released a report in which it says that the probable cause of the collapse of the Florida International University pedestrian bridge was load and capacity calculation errors made by FIGG Bridge Engineers.

The bridge collapsed in March 2018 leading to the death of six people and injuring ten people.

The prefabricated bridge – which was 53m long and weighed 950 tonnes – had only been in place for five days before it fell directly onto the highway, crushing cars beneath it.

The board also found that consulting engineer Louis Berger Group failed to notice FIGG’s design calculation errors that contributed to the collapse.

The NTSB also noted that Louis Berger was not qualified as an independent peer review engineering firm by the Florida Department of Transport and did not have a sufficient budget to evaluate the nodes or the stages of bridge construction.

The NTSB offered 30 findings in total, including that the cracks should have indicated to the project team that the bridge was failing.

The accident has also resulted in the main contractor involved in the bridge, Magnum Construction Management (MCM), filing for bankruptcy protection.

“Errors in bridge design, inadequate peer review and poor engineering judgment led to the collapse of this bridge,” said NTSB chairman Robert Sumwalt. “The failure of all concerned parties, to recognize and take action on the threat to public safety presented by the significant observed bridge structure distress prior to the collapse, led to the tragic loss of life in this preventable accident.”

 

MAGAZINE
NEWSLETTER
Delivered directly to your inbox, World Construction Week Newsletter features the pick of the breaking news stories, product launches, show reports and more from KHL's world-class editorial team.
Longer Reads
7 ways construction is tackling sustainability
As the need for sustainability becomes more apparent across the globe, firms are launching new proposals to meet these growing demands
10 ways to join the hydrogen power revolution
Interest in the use of hydrogen has soared over the past few years as the construction industry races to reduce its carbon footprint. We roundup some recent initiatives
Telescopic boom lifts - the trends
Higher capacities and 100% electric models are the trend. And what lies ahead for 200ft models, or above?
CONNECT WITH THE TEAM
Andy Brown Editor, International Construction Tel: +44 (0) 1892 786 224 E-mail: andy.brown@khl.com
Simon Kelly Sales Manager Tel: +44 (0) 1892 786 223 E-mail: simon.kelly@khl.com
CONNECT WITH SOCIAL MEDIA